stock & financial message boards
  Login  |  Register |  Site Map  |  Blogs |  Recent Activity  |  Members  | Glossary
Ticker/Industry
  Joined Today: 0

« Previous | Next » | All Messages |  GSS Message Board Home | recommend post |  Ignore Poster

Message #46
From: Stock News Bot
Date: January 10, 2007 06:17:00 AM

GSS News Golden Star Reports Progress in Commissioning of Bogoso Sulfide Expansion Project

DENVER--(BUSINESS WIRE)--Golden Star Resources Ltd. (AMEX: GSS)(TSX: GSC) today updated progress on its Bogoso Sulfide Expansion Project at the Bogoso/Prestea property in Ghana.

The current status of the construction and commissioning activity is as follows:

  • The 2,200 tonnes per hour gyratory crusher was commissioned in October and is fully operational, crushing low grade carbonate ore for non-refractory circuit feed;
  • The new ball mill was commissioned in October and the semi-autogenous grinding mill was commissioned in December. Both mills are operating and providing non-refractory slurry feed for the carbon-in-leach (“CIL”) circuit;
  • The existing CIL plant continues to process non-refractory ore. The new CIL circuit is operational and processing non-refractory ore, thereby increasing our throughput capacity;
  • The BIOX® Module 1, Reactor Tanks 1 and 2 are operational, utilizing previously stockpiled refractory concentrate. Reactor Tanks 3 and 4 are being commissioned with the build up of inoculate;
  • The BIOX® Module 1, Reactor Tanks 5, 6 and 7 (smaller, secondary tanks) are expected to be commissioned in February 2007;
  • BIOX® Module 1 coolers and blowers were commissioned in December and are operational;
  • BIOX® Module 1 neutralization tanks and counter-current decantation thickeners are expected to be commissioned at the end of January 2007 in time for refractory ore feed in February 2007;
  • The new flotation circuit (not required until refractory ore is milled) is 70% complete with completion expected in February 2007. An expansion to the flotation circuit which commenced in 2006, is expected to be commissioned in March 2007;
  • The new elution plant (not required until all BIOX® tanks are commissioned) is progressing according to schedule;
  • Paddock dam transfer pumping and piping system to feed stockpiled refractory concentrate to the BIOX® plant is operational;
  • Stockpile buildup of refractory ore is advanced and approximately one million tonnes have been placed on the stockpile; and
  • Work on other areas which are not required until all BIOX® tanks are full is well progressed.

Once we begin to mill refractory sulfides (expected to begin in February 2007) we plan to cease processing oxide ore through the sulfide plant and to start processing refractory sulfide ore. This should allow the flotation circuit to be commissioned and flotation concentrate to be fed to the BIOX® tanks on a continuous basis. Oxide and non-refractory sulfide ores will continue to be processed through the existing Bogoso CIL plant as currently configured.

Peter Bradford, President and CEO said: “We are generally pleased with the construction and commissioning of the Bogoso Sulfide Expansion Project. The BIOX® Module 1 is in partial operation, has been loaded with sulfide concentrate and the inoculation process continues. Of note, the bacteria have responded very well to the sulfide concentrate feed with good activity levels. Typical commissioning problems for plants of this size and complexity have arisen but we are encouraged by the speed and efficiency of our personnel, the consultants and contractors on site to resolve them. We now expect Module 1 of the BIOX® circuit to be fully commissioned in February, Module 2 to be commissioned in March and design operating throughput to be achieved soon thereafter and ramp up to design metallurgical recoveries over the following few months.”

Company Profile

Golden Star holds a 90% equity interest in the Bogoso/Prestea and Wassa open-pit gold mines in Ghana. In addition, Golden Star has an 81% interest in the currently inactive Prestea Underground mine in Ghana, as well as gold exploration interests elsewhere in Ghana, in other parts of West Africa and in the Guiana Shield of South America. Golden Star has approximately 208 million shares outstanding.

Statements Regarding Forward-Looking Information: Some statements contained in this news release are forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. Investors are cautioned that forward-looking statements are inherently uncertain and involve risks and uncertainties that could cause actual results to differ materially. Such statements include comments regarding the timing of the completion, commissioning, and commencement of operations of the Bogoso Sulfide Expansion Project and various components of the Project. Factors that may affect such commencement of operations include delays in receiving needed equipment and parts, design modifications during commissioning, power shortages and interruptions, weather including excessive rainfall or drought. There can be no assurance that future developments affecting the Company will be those anticipated by management. Please refer to the discussion of risk factors in our Form 10-K for 2005.

« Previous | Next » | All Messages |  GSS Message Board Home | Ignore Poster